Bridge Street Reconstruction
Project Summary: Scope of work includes reconstruction of Bridge Street between Flint Street and Boston Street and a section of Goodhue Street. The proposed roadway work will realign Bridge Street and construct separated bicycle facilities on both sides of the roadway. There will be geometric changes made at the both the Boston Street and Flint Street intersections. Boston Street will receive new pedestrian signals and Flint Street intersection will receive all new traffic and pedestrian signals. The project will also include roadway pavement milling and resurfacing, ADA compliant sidewalks, crosswalks and ramps, drainage modifications, new LED lighting, new signage and pavement markings, new tree plantings, and construction of bio-swales and other landscape areas.
Latest Update: FINAL PAVING ON BRIDGE STREET FROM FLINT STREET TO BOSTON STREET AND GOODHUE STREET IS SCHEDULED FOR MONDAY, NOVEMBER 8TH AND TUESDAY, NOVEMBER 9TH.
Two-Week Look Ahead Notices
10-09-2020 | 11-02-2020 | 12-18-2020 | 01-07-2021 | 09-25-2021 | |
03-01-2021 | 03-11-2021 | 04-11-2021 | 05-08-2021 | 05-16-2021 | |
06-12-2021 | 06-26-2021 | 07-10-2021 | 07-11-2021 | 08-14-2021 | |
Notices & Agendas
Preconstruction Meeting Agenda |
| ||
Helpful Hints & Additional Information
Helpful Hints During Constructions | Continuation of Special Needs Form | Project Plans |
Preconstruction Meeting Presentation | Order of Conditions |